2 new bar screens on PR

Jun 22, 2020

In the Isère department, we recently equipped two lift stations with bar screens/compaction screws. These are the 97th and 98th FB Procédés bar screens installed in the department.

The first is traditionally installed in a channel. The second is installed directly in the substation, against the vertical wall.

Both types of installation are perfectly feasible on new or existing structures. The choice often depends on the context or the operating comfort required.

Our technology (upstream screen/upstream discharge) has the advantage of preserving a "fundamental" for optimal waste handling: cleaning the screen from upstream.

Don't hesitate to contact us for advice and to explain the subtleties of our "unique" technology.

TECHNICAL DATA

Supply of a bar screen/compactor assembly on PR Golf

  • Screen type XG12installed in a canal
  • ALL STAINLESS STEEL 304L
  • Width 1500mm
  • Max. flow 2110m3/h
  • 10mm air gap
  • Depth under countertop 1900mm

Options retained

  • Compacting screw type VCP250
  • Automatic bagger
  • Safety pack
  • FB Procédés" control panel for overall management
  • On-site transport

Supply of a bar screen/compactor assembly on PR Charmes

  • Screen type NG21installed in a ∅2500mm substation
  • ALL STAINLESS STEEL 304L
  • WIDTH 1000mm
  • Max. flow 860m3/h
  • 10mm air gap
  • Depth under countertop 3900mm
  • Emergency manual basket

Options retained

  • Compacting screw type VCP250
  • Automatic bagger
  • Safety pack
  • FB Procédés" control panel for managing the entire system
  • On-site transport

Project photos

degrilleur en canal

PR du Golf - Downstream set

degrilleur en poste

PR Charmes - Downstream assembly

degrilleur en canal

PR du Golf - Upstream set

degrilleur en poste

PR Charmes - Upstream assembly